Minnesota Department of Transportation Logo
Home | About Mn/DOT | Doing Business | Getting Around |
511 Traveler Information
Mn/DOT A to Z | Contact | Simple Search | Advanced Search |

US Highway 10 Wadena Project
Bluffton to Wadena

Project Home
blank blank
Overview
blank blank
Project Maps
blank blank
Local District
blank blank
Project Contacts

Contact

Project Manager
Lori Vanderhider, PE
1000 Highway 10 West
Detroit Lakes, MN 56501
218-846-7955
email »


  1. What project is being considered for US Highway 10 at Wadena?
  2. What is the purpose of this highway improvement project?
  3. What is the schedule for the project?
  4. What is the environmental review process?  Why is it done?
  5. Who is managing the project and doing the work?
  6. When will I know if the project will affect my home or business?
  7. What roles do the City of Wadena and Wadena County play?
  8. How can I get involved in this project?
  9. Where can I get more information?

1. What project is being considered for US Highway 10 at Wadena?

A 6.1-mile segment of US Highway 10 through Wadena is the only remaining two-lane segment of this road in the state.  This two-lane segment begins at Bluffton in Otter Tail County and extends eastward to a point 1.5 miles east of Wadena.  The plan is to expand the two-lane segment to four lanes, either along the existing alignment of Highway 10, or using one of three bypass alternatives that skirt the city on the north.  

Go to Top

 

2. What is the purpose of this highway improvement project?

The US Highway 10 Wadena project has been proposed for a number of reasons. The portion of Highway 10 that travels through Wadena is the final remaining two-lane segment on this corridor. All other segments of the highway have been expanded to four lanes (expansion of Highway 10 at Staples began Summer 2007). In addition to completing this system linkage, the project has been proposed in order to prepare for the increased number of trips that are forecast for the system, as well as to correct the existing high number of access points along the highway. Detailed needs and benefit statements are currently being developed for the project's DEIS and should be available Winter 2007/2008.

Go to Top

 

3. What is the schedule for the project?

A Scoping Decision Document was completed in 2004.  This document identified three bypass alternatives (all skirting the city on the north) and a through-town alternative along existing US Highway 10 as alternatives for further study.  The next step is completion of preliminary design for the roadway alternatives and evaluation of the alternatives through an environmental review process.  The project is scheduled for detailed design and acquisition of right-of-way after 2008; construction is anticipated to begin in approximately 2016.

Go to Top

 

4. What is the environmental review process?  Why is it done?

The environmental review process was established by the National Environmental Policy Act (NEPA) passed by Congress in 1972.  NEPA requires completion of an environmental review whenever a project that uses federal funding has the potential to cause environmental, physical, social, or economic impacts.

Although Mn/DOT completed environmental documentation for US Highway 10 in the 1980s, an updated environmental process was begun in 2001 for the 6.1-mile segment of US Highway 10 from Bluffton east through Wadena. Mn/DOT found that environmental regulations concerning wetlands had changed, requiring a reconsideration of the previous alignment.  In addition, the Wadena airport had relocated, making it desirable to look at additional alternatives from a City of Wadena perspective.

The Scoping Decision Document (2004) identified four alternatives and a No-Build Alternative for further study in the Draft Environmental Impact Statement (DEIS).  The Scoping Decision Document also identified the issues that will require detailed study in the DEIS, begun in summer 2006.

The DEIS is intended to provide information to guide decision makers on a proposed action, and is used to evaluate impacts resulting from the proposed alternatives.  For the US Highway 10 project, the DEIS must evaluate these impacts:

  • Bikeways and pedestrian impacts
  • Construction impacts
  • Contaminated sites
  • Economic impacts
  • Erosion control and slope stability
  • Farmland impacts
  • Fish and wildlife
  • Floodplains
  • Groundwater and geology
  • Historic and archaeological resources
  • Land use and land development
  • Noise
  • Park, recreation and open space
  • Right-of-way and relocations
  • Social impacts
  • Stream/water modifications
  • Threatened or endangered species
  • Traffic impacts
  • Vegetation
  • Visual impacts
  • Water quality
  • Wetlands
  • Cumulative Impacts

The DEIS evaluates these impacts for each proposed alternative.  Findings from the DEIS will be presented to the public at an open house, and will be reviewed by state and local officials and agencies during a comment period.

Mn/DOT, as the project manager, will consider the evaluation of alternatives and impacts in the DEIS and comments from the public and local and state agency officials, in identifying a Preferred Alternative.  Mn/DOT’s identification of the Preferred Alternative must be reviewed by the Federal Highway Administration (FHWA), which provides ultimate approval on the Preferred Alternative.

The Final Environmental Impact Statement (FEIS) is focused on the Preferred Alternative and any impacts caused by it.  The FEIS will respond to substantive public and agency comments on the DEIS, and will describe all mitigation required as a result of the impacts caused by the Preferred Alternative.  The FEIS documents Mn/DOT’s and FHWA’s commitment to carrying out the mitigation measures necessary to address Preferred Alternative impacts.

Go to Top

 

5. Who is managing the project and doing the work?

Mn/DOT District 4 (Detroit Lakes) is taking the lead on the project, working closely with Mn/DOT District 3 (Brainerd/Baxter) staff, because the project is located in both Wadena and Otter Tail counties.  Mn/DOT will also work with local and state governments and agencies, both formally with the Policy/Technical Advisory Committee (PTAC) and informally, as the need arises.

Mn/DOT has retained SRF Consulting Group, Inc. to complete preliminary engineering on the alternatives and to complete a Draft and Final Environmental Impact Statement over the next two years.

Go to Top

 

6. When will I know if the project will affect my home or business?

Throughout the environmental review process, Mn/DOT will consider the project’s impact on residences, businesses and agriculture.  These impacts will be examined for all the alternatives, and will be developed in greater detail when a Preferred Alternative is identified (2008).  At that time, property owners will be updated on the project status and Mn/DOT’s anticipated plans for moving ahead with potential acquisition of any property.

Go to Top

 

7. What roles do the City of Wadena and Wadena County play?

Representatives from the city, county and other local governments such as townships, have been invited to sit on the Policy/Technical Advisory Committee (PTAC), a group that meets regularly to review on-going work on the DEIS and on the development of the proposed roadway alignments.  These representatives will update their respective groups and bring comments from them to the PTAC meetings as the project proceeds.

The decision on a Preferred Alternative will be made by Mn/DOT, with the concurrence of the Federal Highway Administration (FHWA).  Local governments may offer comments as part of the public participation process, and Mn/DOT and FHWA will consider these comments in their decision making.

Go to Top

 

8. How can I get involved in this project?

  • Check this website regularly for updated information.
  • Come to the open houses to learn about the alternatives and the impacts associated with them—another open house will be held later this year.
  • Send your comments and concerns to the Mn/DOT Project Manager (see below).

Go to Top

 

9. Where can I get more information?

For additional information on this project, contact the Mn/DOT Project Manager:

Project Manager
Lori Vanderhider, PE
1000 Highway 10 West
Detroit Lakes, MN 56501
218-846-7955
email »

Go to Top

 

 

 

 

 

blank












blank

© 2000-2005 Minnesota Department of Transportation
395 John Ireland Boulevard St. Paul, MN 55155-1899
Phone: 800/657-3774 800/627-3529 (TTY, Voice, ASCII)
This site best viewed with 1024X768 or greater and
with Netscape 4.7 or Internet Explorer 4.5 or greater.

A to Z | Getting Around | About Mn/DOT | Doing Business | Contact Mn/DOT | News Room | 511 Traveler Service | Careers/Jobs | Links | Northstar | Governor's Site |