Minnesota Department of Transportation Logo
Home | About Mn/DOT | Doing Business | Getting Around |
511 Traveler Information
Mn/DOT A to Z | Contact | Simple Search | Advanced Search |

US Highway 10 Wadena Project
Bluffton to Wadena

Project Home
blank blank
Overview
blank blank
Project Maps
blank blank
Local District
blank blank
Project Contacts
Contact

Project Manager
Lori Vanderhider, PE
1000 Highway 10 West
Detroit Lakes, MN 56501
218-846-7955
email »

What is an EIS?

The current study to evaluate alternatives and impacts on US Highway 10 is an Environmental Impact Statement (EIS).  An EIS is a full disclosure document used to evaluate impacts of a proposed action and to provide information to guide decision-making on a proposed action. An EIS has two parts:  a Draft EIS (DEIS) and a Final EIS (FEIS).

The Draft EIS is intended to provide information for governmental units, the proposer of the project and other persons to:

  • Evaluate a proposed project which has the potential for significant environmental effects
  • Consider alternatives to the proposed project
  • Explore methods for reducing adverse environmental effects

The Draft EIS discusses:

  • Purpose and need of the action
  • Reasonable alternatives
  • Summarizes the studies, reviews, consultation and coordination required to complete this stage of the environmental process.

The Final EIS documents:

  • The citizen involvement process (see public involvement)
  • Responds to substantive comments received on the DEIS
  • Discusses alternatives considered
  • Identifies a preferred alternative
  • Describes environmental mitigation

The US Highway 10 Wadena Draft EIS process began in Spring 2006 with the first Policy/Technical Advisory Committee and first open house held in June 2006.  The various steps involved in completing the environmental process for the US Highway 10 Wadena project are shown on the schedule below:

Task Tentative Schedule

Prepare Draft Environmental Impact Statement

Winter 2007-2008

DEIS Review by Mn/DOT, FHWA and agencies

Winter 2007-2008

Public Hearing and comment period for DEIS

1 month after DEIS distribution

The Mn/DOT Commissioner identifies a Preferred Alternative after the conclusion of the DEIS public comment period.

The Final EIS will evaluate the impacts of the Preferred Alternative.

Preparation of Final Environmental Impact Statement

Summer 2008

FEIS approval by Mn/DOT and FHWA

Anticipated Fall 2008

 

Go to Top

 

blank












blank

© 2000-2005 Minnesota Department of Transportation
395 John Ireland Boulevard St. Paul, MN 55155-1899
Phone: 800/657-3774 800/627-3529 (TTY, Voice, ASCII)
This site best viewed with 1024X768 or greater and
with Netscape 4.7 or Internet Explorer 4.5 or greater.

A to Z | Getting Around | About Mn/DOT | Doing Business | Contact Mn/DOT | News Room | 511 Traveler Service | Careers/Jobs | Links | Northstar | Governor's Site |